GovBidAlerts
← All opportunities
This notice has been superseded. See the latest notice: Y--North Gunnison Substation 115kV Switch Install (Solicitation)

North Gunnison Substation 115kV Switch Install

Key dates

Posted
Jun 3, 2026
Response deadline
Jul 6, 2026, 8:00 PM UTC
Archive date
Archive type
auto15

Classification

Notice type
Solicitation
Base type
Presolicitation
Set-aside
Set-aside code
PSC
Y1PZ

NAICS

Issuing office

Department
ENERGY, DEPARTMENT OF
Sub-tier
ENERGY, DEPARTMENT OF
Office
WESTERN-ROCKY MOUNTAIN REGION
Office code
089.8900.895032
Organization type
OFFICE
Office address
LOVELAND, CO, 80538, USA

Place of performance

Street
Street 2
City
State
Zip
Country

Contacts

Description

North Gunnison 115-kV Switch Installation to add a 115kV Disconnect Switch to the bus work to provide flexible operation to feed the North Gunnison loads and allow WAPA to maintain all the electrical substation equipment. a. Provide demolition and site development. b. Remove and dispose of existing pedestals, rigid bus, insulators, and concrete foundations. c. Furnish and install 115kV disconnect switch, structural steel, foundations, and associated equipment.

Other notices in this solicitation

Similar open contracts

Metadata

Notice ID
b928e18c9a454962905eff759bd3ee34
Full path
ENERGY, DEPARTMENT OF.ENERGY, DEPARTMENT OF.WESTERN-ROCKY MOUNTAIN REGION
Office code
089.8900.895032
Ingested
Jun 4, 2026
Updated
Jul 11, 2026