GovBidAlerts
← All opportunities

Gavins Point Crane Rail Replacement

Key dates

Posted
Jul 23, 2026
Response deadline
Aug 10, 2026, 7:00 PM UTC
Archive date
Archive type
autocustom

Classification

Notice type
Presolicitation
Base type
Presolicitation
Set-aside
Set-aside code
PSC
Y1KA

NAICS

Issuing office

Department
DEPT OF DEFENSE
Sub-tier
DEPT OF THE ARMY
Office
W071 ENDIST OMAHA
Office code
021.2100.USACE.NWD.NWO.W9128F
Organization type
OFFICE
Office address
OMAHA, NE, 68102-4901, USA

Place of performance

Street
Street 2
City
State
Zip
68730
Country

Contacts

Description

On or about 10 August 2026, the Government intends to issue a solicitation for Gavins Point Crane Rail Replacement. The solicitation will close on or about 29 September 2026. The solicitation is Unrestricted and Open to Both Large and Small Business Participation. A Site Visit will be scheduled and additional information regarding the site visit will be provided in the solicitation via FAR Clause 52.236-27. The site visit is tentatively scheduled for 26 August 2026.This project will involve removal and replacement of the Gavins Point Powerhouse Intake crane runway rail located near Yankton, South Dakota. The 80-ton Gavins Point Intake Gantry Crane rail shall be installed and aligned to Crane Manufacturers Association of America, CMAA 70 standards.The total length of the rails is 328 ft x 2 centerline of rail to the powerhouse wall. The work will include an initial survey of the rail alignment, existing grout pocket condition, demolition and removal of existing intake crane rail and components, rail clips, asphalt, base plates, and non-shrink grout. Demolition and removal of the existing concrete anchors will be based on the concrete imaging reports, and the grout pocket condition assessment between each anchor pair along the deck. For bidding purposes, it is assumed 80 percent of the existing anchors will be replaced and all concrete anchors at joint bars will be replaced. The contractor will provide anchors suitable for use in cracked concrete and under seismic loading. Once the rail and hardware are replaced and aligned to the required standards the grout pockets will be filled with two-component aliphatic polyurethane elastomer grout along the full length of the intake crane runway as shown on the drawings. The sequencing of demolition and installation of the crane rails must minimize project time without an operational intake crane and typically progress from one side of the dam to the other with the transfer of the crane from old to new rail during completion of the final rail segment. The Contractor will be required to commence work upon receipt of contract award and complete the work 360 calendar days after receipt of Notice to Proceed, this is subject to change after solicitation issuance. The estimated construction cost of this project is between $1,000,000 and $5,000,000. The Primary North American Industry Classification System (NAICS) code anticipated for solicitation is 238120 ? Structural Steel and Precast Concrete Contractors, with a size standard for Small Business of $19M. All questions shall be submitted on ProjNet (ProjNet access, and additional guidance, will be given at time of solicitation issuance). The Contracting Office is USACE Omaha District, 1616 Capital Ave, Omaha, NE 68102. The Place of Performance is Gavins Point Project, Crofton, NE 68730.

Similar open contracts

Metadata

Notice ID
a638ea847f974750935ba05c05a74dfb
Full path
DEPT OF DEFENSE.DEPT OF THE ARMY.W071 ENDIST OMAHA
Office code
021.2100.USACE.NWD.NWO.W9128F
Ingested
Jul 24, 2026
Updated
Jul 24, 2026