PresolicitationActiveW912DR26BA004_
Q4 FY26 Baltimore Harbor and Channels Maintenance Dredging, Maryland Channels, Chesapeake Bay, MD
DEPT OF DEFENSE / DEPT OF THE ARMY / W2SD ENDIST BALTIMOREKey dates?
- Posted?
- Jun 24, 2026
- Response deadline?
- Jul 10, 2026, 8:00 PM UTC
- Archive date?
- —
- Archive type?
- autocustom
Classification?
- Notice type?
- Presolicitation
- Base type?
- Presolicitation
- Set-aside?
- —
- Set-aside code?
- —
- PSC?
- Z1KF
NAICS?
Issuing office?
- Department?
- DEPT OF DEFENSE
- Sub-tier?
- DEPT OF THE ARMY
- Office?
- W2SD ENDIST BALTIMORE
- Office code?
- 021.2100.USACE.NAD.NAB.W912DR
- Organization type?
- OFFICE
- Office address?
- BALTIMORE, MD, 21201-2526, USA
Place of performance?
- Street?
- Baltimore, MD
- Street 2?
- —
- City?
- —
- State?
- —
- Zip?
- 21201
- Country?
- —
Contacts?
- Ashley Flahertyprimary
Description?
The project consists of maintenance dredging approximately 2,250,000 cubic yards (cy) from the deep-draft federal navigation channels serving the Port of Baltimore. The work is to be performed between November 2026 through March 2027. The dredging depth for all channels is 50 feet mean lower low water (ft MLLW) with an additional 1 ? 2 foot of allowable overdepth. Approximately 1,538,000 cy will be dredged from the Maryland approach channels (Craighill Entrance, Craighill Angle, Cutoff Angle, and Upper Range Channels) and placed at the Paul S. Sarbanes Ecosystems Restoration Project at Poplar Island. Approximately 700,000 cy will be dredged from Baltimore Harbor Channels (Brewerton Angle and Curtis Bay Channels) and placed at the Cox Creek Dredged Material Containment Facility. The estimated magnitude of construction is between $25,000,000.00 and $100,000,000.00. The work areas are within heavy commercial waterways supporting the Port of Baltimore. The equipment required for this work commonly consists of two 30 plus cubic yard clamshell dredges, one 24 ? 30-inch hydraulic unloader, six to eight large tugs, six to eight 2,500 ? 6,000 cubic yard material scows, a drag bar and barge, and appropriate attendant plant and pipeline. The material will be dredged by clamshell/bucket and scow and placed within a period of performance of approximately 120 calendar days from receipt of Notice-to-Proceed. THE SOLICITATION IS SCHEDULED TO BE RELEASED ON/OR ABOUT 10 JULY 2026.
Similar open contracts
Metadata?
- Notice ID?
- 9c88cf1b086e418f9e76cb711b0ad562
- Full path?
- DEPT OF DEFENSE.DEPT OF THE ARMY.W2SD ENDIST BALTIMORE
- Office code?
- 021.2100.USACE.NAD.NAB.W912DR
- Ingested?
- Jun 25, 2026
- Updated?