Y1DA--NRM-CONST 630A4-17-433 Replace Boiler Plant Main Electrical Switchgear

Key dates

Posted
May 19, 2026
Response deadline
May 26, 2026, 4:00 PM UTC
Archive date
Archive type
autocustom

Classification

Notice type
Solicitation
Base type
Solicitation
Set-aside
Set-aside code
PSC
Y1DA

NAICS

Issuing office

Department
VETERANS AFFAIRS, DEPARTMENT OF
Sub-tier
VETERANS AFFAIRS, DEPARTMENT OF
Office
242-NETWORK CONTRACT OFFICE 02 (36C242)
Office code
036.3600.36C242
Organization type
OFFICE
Office address
ALBANY, NY, 12208, USA

Place of performance

Street
Street 2
City
State
Zip
Country

Contacts

Description

60. RFI #18 states: Please provide hazardous materials survey information for asbestos, lead paint, refrigerants, contaminated oil, and other regulated materials in demolition areas. VA Response states: Hazardous sampling and abatement are required. GC to provide abatement service, A/E to provide Air Monitoring service Since there are no drawings or specifications, please clarify in detail the scope of work for the abatement service, including the quantities for hazardous sampling and abatement. Also, identify the work on drawings. This will help the contractor/GC provide a fair and reasonable price to the government. Updated VA Response: Please be advised that no pre demolition hazardous materials survey has been performed for asbestos, etc. Accordingly, each bidder shall include a reasonable allowance based on construction perimeter or square foot in their bid for all necessary hazardous materials survey, sampling, testing, and abatement services required to complete the work in compliance with applicable codes and regulations. This allowance shall cover, at a minimum, the costs for engaging qualified environmental consultants conducting field investigations and sampling, laboratory analysis, and performing any required abatement, removal, handling, and proper disposal of identified hazardous/regulated materials encountered within the demolition and construction areas. The contractor remains responsible for confirming the adequacy of the allowance and for executing all required hazardous materials work in accordance with governing federal standards. Any adjustments to the allowance, if warranted based on actual conditions, will be addressed in accordance with the contract s provisions for changes.

Attachments (19)

Other notices in this solicitation

Similar open contracts

Metadata

Notice ID
7e1c1990385a4f3ba2cf6c3174bb6004
Full path
VETERANS AFFAIRS, DEPARTMENT OF.VETERANS AFFAIRS, DEPARTMENT OF.242-NETWORK CONTRACT OFFICE 02 (36C242)
Office code
036.3600.36C242
Ingested
May 20, 2026
Updated
Jun 25, 2026