closed🌐 lakelandgov2024-ITB-294

SETTING OF 11 LARGE STEEL TRANSMISSION POLES, SUBSTATION PIER FOUNDATIONS, SIDEWALK/RAILING REALIGNMENT AND CONSTRUCTION ASSISTANCE FOR THE NEW 69KV TRANSMISSION LINE

lakelandgov / LE - Engineering

Description

The intent of this bid is to have the Contractor install 11 large steel poles, install two (2) pier foundations at the Dranefield Substation, remove and realign sidewalk/railing at the W Pipkin Bridge and assist Lakeland Electric crews with removing and installing additional poles as needed. The Contractor shall provide all management, administration, tools, construction equipment, labor and supervision to accomplish the work as specified herein and on the Construction Drawings. Materials will be furnished by the Owner.

Details

Posted
Aug 20, 2024
Response deadline
Sep 24, 2024, 7:30 PM UTC
Status
closed
Buyer
lakelandgov
Department
LE - Engineering
Jurisdiction
lakelandgov
Reference #
2024-ITB-294
Summary
<p>The intent of this bid is to have the Contractor install 11 large steel poles, install two (2) pier foundations at the Dranefield Substation, remove and realign sidewalk/railing at the W Pipkin Bri
Is Paused
false
Template Title
Invitation To Bid
Copy Count
0
Government Organization City
Lakeland
Government Organization Name
City of Lakeland
Government Organization State
FL
Government Organization Website
https://www.lakelandgov.net/
Government Organization Zip Code
33801
Government Organization Address1
1140 E. Parker Street
Government Organization Timezone
America/New_York
Government Organization Country Code
US
Government Organization Phone Country
1
Closed Substatus
awarded

Contact

(863)834-6780
Finding similar opportunities…

This listing is a summary from lakelandgov's open procurement data. We ingest every field the feed publishes; the full solicitation documents are on the source portal.

Raw record
{
  "id": 111093,
  "_slug": "lakelandgov",
  "title": "SETTING OF 11 LARGE STEEL TRANSMISSION POLES, SUBSTATION PIER FOUNDATIONS, SIDEWALK/RAILING REALIGNMENT AND CONSTRUCTION ASSISTANCE FOR THE NEW 69KV TRANSMISSION LINE",
  "status": "closed",
  "summary": "<p>The intent of this bid is to have the Contractor install 11 large steel poles, install two (2) pier foundations at the Dranefield Substation, remove and realign sidewalk/railing at the W Pipkin Bridge and assist Lakeland Electric crews with removing and installing additional poles as needed. The Contractor shall provide all management, administration, tools, construction equipment, labor and supervision to accomplish the work as specified herein and on the Construction Drawings.&nbsp; Materials will be furnished by the Owner.</p><p>&nbsp;</p>",
  "isPaused": false,
  "template": {
    "title": "Invitation To Bid"
  },
  "addendums": [
    {
      "id": 47990
    },
    {
      "id": 47043
    }
  ],
  "copyCount": 0,
  "isPrivate": false,
  "comingSoon": false,
  "created_at": "2024-08-15T16:53:27.715Z",
  "department": {
    "id": 3227,
    "name": "LE - Engineering"
  },
  "government": {
    "code": "lakelandgov",
    "organization": {
      "city": "Lakeland",
      "logo": "https://assets.procurement.opengov.com/logo-uploads/1e1203f1-dfab-4985-bac3-5fcf91c902cc_COLbrand_Main_Color.jpg",
      "name": "City of Lakeland",
      "phone": "(863)834-6780",
      "state": "FL",
      "website": "https://www.lakelandgov.net/",
      "zipCode": "33801",
      "address1": "1140 E. Parker Street",
      "address2": null,
      "phoneExt": null,
      "timezone": "America/New_York",
      "countryCode": "US",
      "phoneCountry": "1"
    }
  },
  "financialId": "2024-ITB-294",
  "closeOutReason": null,
  "closedSubstatus": "awarded",
  "proposalDeadline": "2024-09-24T19:30:00.000Z",
  "releaseProjectDate": "2024-08-20T16:56:09.655Z"
}